The Brihanmumbai Municipal Corporation (BMC) will begin girder launching for the new bridge connecting Bandra and Dharavi over the Mithi River. The work marks the second phase of a ₹204 crore project to widen the existing bridge to 10 lanes. The redevelopment is also expected to improve the river’s flow and ease traffic movement between Mumbai’s suburbs and South Mumbai. Scroll down to know more.
BMC’s ₹204 Crore Bandra-Dharavi Bridge Project Is To Be Built In Three Phases
The project is part of the Mithi River basin widening plan. The civic body intends to demolish the nearly 50-year-old bridge and replace it with a wider structure. The project received final approvals in 2019, following which the BMC began construction in phases.
The bridge begins near the Jio World Drive road junction at Bandra Kurla Complex (BKC), along the Western Express Highway, and ends near Dharavi, around 110 metres south of the Mithi River. Once completed, it is expected to ease congestion for commuters travelling between BKC, Dharavi and Mahim Causeway.
Also Read: Kareena &; Hrithik Reunite After 25 Yrs As Airbnb Brings K3G’s Raichand House To Life In Mumbai
The construction is being carried out in three phases. In the first phase, the BMC built a new bridge on the western side of the existing structure. The second phase involves constructing another bridge on the eastern side. In the final phase, traffic will be shifted to the two newly built bridges. The civic body will then demolish the old bridge and redevelop the space.
Girder Launching To Begin For The Second Phase Of Construction
A senior BMC official told The Indian Express that the project was planned to widen the Mithi River in line with the Chitale committee’s recommendations. The new bridge is also expected to improve connectivity for commuters travelling between the suburbs and South Mumbai.
Also Read: Four Seasons Hotel Mumbai Wins Michelin Key For Its Contemporary Luxury Experience
The official added that work on the first phase has been completed, while construction of the second phase is underway. The girders have arrived at the site, and their assembly is in progress.
Good news for Mumbai commuters.
Cover Image Courtesy: Wikimedia Commons
FAQs
Why is the BMC rebuilding the Bandra-Dharavi bridge?
The BMC plans to replace the nearly 50-year-old bridge with a wider 10-lane structure as part of the Mithi River basin widening project.
How much will the Bandra-Dharavi bridge project cost?
The project is estimated to cost ₹204 crore.
How many phases will the bridge construction have?
The project is being executed in three phases. The first phase is complete, the second is underway, and the final phase will involve diverting traffic to the two new bridges before demolishing the old structure.