If Al Qudra Road is part of your daily drive, the construction you have been driving beside all year is finished. Dubai’s Roads and Transport Authority (RTA) has completed all bridge works under the Al Qudra Street intersection development project.
What Has Opened
Newly completed bridges and access ramps extending 2,660 metres are now open at the Al Qudra Street and Sheikh Zayed bin Hamdan Al Nahyan Street intersection, providing seamless traffic movement across all routes.
Earlier phases are already in use. A 700-metre, four-lane bridge for traffic heading towards Al Qudra City opened in August and can take up to 6,000 vehicles per hour, and the matching bridge for the opposite direction opened in February.
The junction’s design, as RTA outlined earlier this year, includes a 500-metre bridge for traffic heading towards Jebel Ali and a 900-metre bridge for those going towards Downtown Dubai and Dubai International Airport.
The Numbers
RTA says the intersection’s capacity has risen by 150 per cent. Its earlier figures put this at a jump from 7,800 to 19,400 vehicles per hour.
RTA puts the cut in journey time along the upgraded corridor at 70 per cent, from 9.4 minutes to 2.8. That works out to roughly seven minutes saved.
Who Will Feel The Difference
The works have opened in stages since February, so many regular drivers have already seen parts of the project in use.
Reaching more than 400,000 residents and visitors, the project links key Dubai communities—including Arabian Ranches 1 and 2, Dubai Motor City, Dubai Studio City, Akoya, Mudon, and DAMAC Hills, according to the RTA.
Also Read: This New Bridge In Dubai’s Al Qudra Cuts Travel Time To Just 2.8 Minutes; Here’s All About It
Part Of A Bigger Upgrade
The junction is one piece of the wider Al Qudra Road Development Project. It covers upgraded intersections, 4,000 metres of bridges and the widening and development of 11.6 kilometres of the road, running from Sheikh Mohammed bin Zayed Road to Emirates Road.
Earlier this year, RTA opened a 600-metre bridge at the Al Qudra Road junction with the link road connecting Arabian Ranches and Dubai Studio City. That one lifted capacity from 6,600 to 19,200 vehicles per hour. In May, improvements at the Emirates Road and Al Qudra Road intersection also opened.
RTA has also been adding lanes on both sides of Emirates Road over a combined 4.8-kilometre stretch, to improve access to the surrounding developments. The February bridge had already cut waiting time at its junction by 55 per cent, from 113 seconds to 52.
Cover Image Courtesy: Dubai RTA/Website
FAQs
What has Dubai's RTA completed on Al Qudra Road?
RTA has completed all bridge works under the Al Qudra Street intersection development project. The newly opened bridges and ramps at the Al Qudra Street and Sheikh Zayed bin Hamdan Al Nahyan Street junction total 2,660 metres and allow free-flowing traffic in all directions.
How much time will the project save drivers?
RTA says journey time along the upgraded corridor falls by 70 per cent, from 9.4 minutes to 2.8 minutes. That is a saving of roughly seven minutes.