Navi Mumbai Airport Might Get A Spur Line Connecting India’s First Bullet Train; Here’s All About It

The first phase of this bullet train between Vapi and Sabarmati will be ready by December 2027. Plus, the full corridor from Mumbai to Ahmedabad is expected to be operational by December 2029.

by Ashmeet Guliani
Navi Mumbai Airport Might Get A Spur Line Connecting India’s First Bullet Train; Here’s All About It

Mumbaikars, there is some great news! Reports say that the highly anticipated Mumbai-Ahmedabad High-Speed Rail Project—India’s first bullet train— may get a new diversion to the upcoming Navi Mumbai International Airport (NMIA), which is set to be inaugurated soon. Let’s see what the buzz is all about.

India’s First Bullet Train Corridor Might Get A Spur Line To Navi Mumbai Airport

Navi Mumbai Airport Bullet Train
Image Courtesy: Canva Pro/ Dongjie Chen (Representative Image)

Authorities are reportedly planning that the Mumbai-Ahmedabad High-Speed Rail Project might get a spur line to NMIA. However, do not get your hopes up as the plan is still in its initial phases. As per a report by Mid-Day, a proposal has been sent to the Railway Board for consideration.

If the plan materialises, this spur line would connect India’s first bullet train corridor with Navi Mumbai International Airport. It should be noted that NMIA is set to become the second international airport serving the Mumbai metropolitan region after Chhatrapati Shivaji Maharaj International Airport. Its inauguration was reportedly delayed but may take place next month.

Also Read: India’s First Bullet Train Update: Stations On Mumbai-Ahmedabad Corridor Nearing Completion

The Plan Might Boost Connectivity 

According to the same report, the new line could potentially reduce travel time for passengers travelling between Navi Mumbai and Gujarat. However, railway officials have not issued any formal confirmation yet. If approved, this spur line could make NMIA a major intermodal transport hub, integrating air, rail and road travel for seamless and faster passenger movement.

Work on the Mumbai-Ahmedabad High-Speed Rail corridor is progressing steadily. Several milestones have been achieved: In Maharashtra, excavation for the Bandra-Kurla Complex station ( the only underground station on the 508 km route) is nearly 75% complete. Whereas in Gujarat, construction of steel bridges continues, with nine of 17 major bridges already launched. The project is estimated at over ₹1.08 lakh crore and is funded by Japan through JICA. 

As per the same report, Railway Minister Ashwini Vaishnav confirmed that the first phase of this bullet train between Vapi and Sabarmati will open by December 2027. Plus, the full corridor from Mumbai to Ahmedabad is expected to be operational by December 2029.

Also Read: Good News! South India To Get A Bullet Train Connecting These 4 Major Cities, Announces Andhra CM

What do you think of this new plan? Let us know your thoughts in the comments!

Cover Image Courtesy: Supplied and Mumbai–Ahmedabad high-speed rail corridor, Wikipedia/ Toshinori baba

For more such snackable content, interesting discoveries and the latest updates on food, travel and experiences in your city, download the Curly Tales App. Download HERE.
First Published: September 26, 2025 4:44 PM