Home

  /  

India

  /  

Trending

  /  

Mumbai’s Gargai Dam Project Gets Delayed: When Will Construction Finally Begin?

Mumbai’s Gargai Dam project is an important water supply project planned in Palghar. However, its construction has now been delayed to next year.

by Priyanshi Shah
Mumbai’s Gargai Dam Project Gets Delayed: When Will Construction Finally Begin?
Cover Image Courtesy: Canva Pro/ zorotoo's (Representative Image)

Many infrastructure projects are currently in progress in Mumbai, including several projects aimed at improving the city’s water supply. One such project is the Gargai Dam in Palghar. However, the project has now faced a delay, with construction pushed to next year. Here’s everything you need to know about the latest update.

Why Gargai Dam Project In Mumbai Delayed?

The Gargai Dam project was expected to begin in October 2026, but it has now been pushed to January 2027. According to BMC plans, the Gargai Dam will be built in Wada tehsil of Palghar district. It is around 110 km from Mumbai.

According to Mid Day report, once the project is completed, the dam will supply 440 million litres of water to Mumbai every day. It will help address one of the major water-related problems in the city. However, the project has been delayed because two approvals are still pending.

 It needs permission from the Ministry of Environment, Forest and Climate Change (MoEFCC) and approval from the National Board for Wildlife. The approvals are needed because the project will submerge around 3,10,140 trees. It will also include transplanting these trees and rehabilitating residents and landowners affected by the construction. 

Also Read: Mumbai Coastal Road To Get A “Green Necklace”? Zoo To Food Outlets, Whats In The Future?

What Is The Progress Of The Project?

BMC officials are working to get the pending permissions so that construction can begin by January. As per Mid Day report, once the approvals come through, the BMC will start rehabilitating affected landowners and transplanting trees. Meanwhile, soil testing, project design and planning are already underway. Officials also said that the availability of alternative land is no longer an issue. 

The project has a total budget of ₹5,000 crore, including construction and other related work. The dam construction cost is around ₹3,100 crore. The BMC aims to complete the dam and the tunnel connecting it to Modak Sagar reservoir by 2028. 

What are your thoughts on this? Tell us in the comments below!

Also Read: Ayodhya Gets New Wings As Direct Flights To Delhi, Bengaluru And Mumbai Take Off This October

Cover Image Courtesy: Canva Pro/ zorotoo’s (Representative Image)

FAQs

When will the construction of Mumbai’s Gargai Dam begin?

The construction of Gargai Dam in Mumbai will begin in January 2027.

Which places in Mumbai are famous?

Gateway of India, Marine Drive, Juhu Beach and Colaba are among Mumbai’s popular places.

How many days are enough to explore Mumbai?

2-3 days are enough to explore Mumbai.

Priyanshi Shah | Content Writer

Priyanshi Shah is a Content Writer at Curly Tales with 4 years of experience in writing. She loves writing about fashion, food, travel and entertainment. She has completed her graduation with a Bachelor of Business Administration (Marketing) from Gujarat University in Ahmedabad. What keeps Priyanshi going is hot chocolate, books and rom-com movies.

For more such snackable content, interesting discoveries and the latest updates on food, travel and experiences in your city, download the Curly Tales App. Download HERE.
First Published: September 30, 2026 8:55 PM