Why Are Mumbai Metro’s Green Line 4 & Pink Line 6 Still Incomplete After 8 Years?

Mumbai's Metro network is growing, but not all projects are progressing as expected. Green Line 4 and Pink Line 6 have faced several delays over the years.

by Priyanshi Shah
Why Are Mumbai Metro’s Green Line 4 & Pink Line 6 Still Incomplete After 8 Years?
Cover Image Courtesy: Wikipedia/ Mumbaimetro

Mumbai Metro is expanding, giving commuters a convenient travel option across the city. While new routes are being introduced, work on some corridors has been stuck for years. Work on Orange Line 5 is moving quickly; however, Green Line 4 and Pink Line 6 continue to face delays. Scroll down to know why!

Why Are Mumbai Metro Lines 4 & 6 Facing Delays?

The work on Mumbai Metro Green Line 4 and Pink Line 6 has been delayed for over eight years. Not one, but several factors are behind these delays. According to Mid Day, these include land acquisition issues, incomplete stations, depot-related complications and repeated deadline extensions. These two elevated corridors are important to improve connectivity. Together, these two lines have 43 stations and are worth ₹21,265 crore.

How Much Work Is Completed On Green Line 4?

According to the Mumbai Metropolitan Region Development Authority’s (MMRDA) report dated August 31, 2026, Green Line 4 had completed:

  • 95% of pier construction
  • 94% of U-girder work 
  • 92% of deck-slab work.

But there is still some work pending. This project faced land acquisition issues in Vikhroli East. However, after years of legal proceedings, the Metro authorities finally received possession of the 16,762-square-metre Laxmi Nagar plot in March 2026, which cost ₹164.31 crore.

Also Read: This Mumbai Temple Has Over 5 Lakh Bells, Each Representing A Fulfilled Wish

What Challenges Is Mumbai Metro Line 6 Facing?

The work on Pink Line 6 hasn’t been easy. As per Mid Day report, it faced challenges at Shyam Nagar station, the JVLR-Eastern Express Highway junction and Kanjurmarg depot. On September 29, 2026, the Supreme Court dismissed the developer’s appeal over the 15-hectare depot land. We hope the work on this line gets completed soon and passengers can finally travel smoothly.

Amid the incomplete work, the Metro authorities have started trial runs on the northern Green Line 4/4A route.

How Many Passengers Will Both Lines Carry?

Once both Green Line 4 and Pink Line 6 are operational, they are expected to see approximately 12.13 lakh and 7.69 lakh daily passengers, respectively, by 2031.

How excited are you to travel on these routes? Tell us in the comments below!

Also Read: Mumbai Metro Launches Aqua Line Passport To Celebrate One Year; Check Cost, Stamp Details & More

Cover Image Courtesy: Wikipedia/ Mumbaimetro

FAQs

Which place has the longest metro network in India?

Delhi has the longest metro network in India.

What is the main mode of transport in Mumbai?

To travel in Mumbai, the main mode of transport is local train.

How to check local train status in Mumbai?

You can check the status of local train in Mumbai on m-Indicator.

What is the price of local train ticket in Mumbai?

The local train ticket prices in Mumbai starts from ₹5.

Priyanshi Shah | Content Writer

Priyanshi Shah is a Content Writer at Curly Tales with 4 years of experience in writing. She loves writing about fashion, food, travel and entertainment. She has completed her graduation with a Bachelor of Business Administration (Marketing) from Gujarat University in Ahmedabad. What keeps Priyanshi going is hot chocolate, books and rom-com movies.

For more such snackable content, interesting discoveries and the latest updates on food, travel and experiences in your city, download the Curly Tales App. Download HERE.
First Published: November 14, 2026 2:08 PM